Recording the progress of a batch

Open: Works Orders > Records > Batch > Amend Works Order.

  1. Select the works order.
  2. Click the Tracking tab.

    All operationsThe labour, machine and tool processes required to manufacture an item. required to complete the works order are listed in sequence order.

  3. To record the progress of production, select an operation.
  4. Click Qty Complete.

    The Qty Complete window appears.

  5. Enter the quantity that has now passed through the selected operation in the Completed box.

    This defaults to the outstanding quantity.

    This quantity is automatically rolled forward as the In Progress quantity for the following operation, leaving any balance still to be completed.

  6. Continue as necessary to record the progress of the works order.
  7. When you have entered a completed quantity for the final operation, the Complete Works Order window appears.
  8. You can now complete the works order.

Go to top